Answer first
Answer first: the document chain from yard gate to foreign flag
Delivery is where a build or refit either concludes cleanly or unravels into months of anchorage time. The chain has four links, and each depends on the previous one being complete.
Delivery is where a build or refit either concludes cleanly or unravels into months of anchorage time. The chain has four links, and each depends on the previous one being complete: (1) the yard closes its side — builder's certificate, protocol of delivery and acceptance, final invoices settled; (2) Indonesian formalities close — export declaration and customs clearance for a newly built vessel leaving as goods; (3) the technical file converts — tonnage certificate, class or survey documents, and equipment records in a form the receiving flag accepts; (4) the flag opens — provisional registration, radio licence, minimum-manning documents, insurance. The desk's role is running links two through four in parallel where the rules allow it, so the calendar shows one handover, not four sequential waits.
Export documentation for newly built vessels
A newly built vessel leaving Indonesia is, administratively, an export shipment that happens to sail itself. The working set: builder's certificate establishing first ownership; the shipbuilding contract and commercial invoice; the export declaration (PEB) lodged through customs; and the protocol of delivery and acceptance dated at handover. Vessels delivered under tow add a towage approval and warranty survey by the tow's insurers. The classic failure is mismatched names and figures across documents — a hull number or tonnage figure that differs between builder's certificate, invoice and measurement papers will stop a registry clerk in any country. We audit the set line-by-line before anything is lodged.
Flag options: Indonesian flag vs foreign registry
The decision is commercial, not sentimental. Indonesian flag suits vessels that will trade domestically — cabotage rules reserve domestic carriage for Indonesian-flagged, Indonesian-owned tonnage, and the vessel stays inside the BKI and national administration system it was built under. Foreign registries suit vessels departing to international trade or charter: owners weigh registration cost and speed, tonnage-tax regimes, acceptance of the vessel's class certificates, crewing rules, and mortgage recording quality. Popular open registries process provisional registration in days once the document file is clean — the file, again, is the schedule.
Tonnage, IMO number and class transfer notes
Three technical items decide how smooth the conversion is. Tonnage: international voyages need a tonnage certificate under the 1969 Convention; measurement is arranged before departure so the receiving registry is not re-measuring remotely. IMO number: required for self-propelled seagoing merchant ships of 100 GT and above on international voyages (with defined exceptions such as certain fishing and pleasure craft); it is issued once for the hull and follows the vessel between flags — newbuilds destined for export should have it assigned during construction, not discovered missing at registration week. Class transfer: when the receiving flag requires a different recognised organisation, the transfer runs to the incoming society’s takeover rules — document review and survey — and is far cheaper to arrange while the vessel still sits at the builder’s yard with its file open.
Delivery logistics: crews, insurance, sea passage
The physical delivery is a project of its own: a delivery crew qualified for the tonnage and route (or a towage plan for unmanned hulls), voyage insurance matching the registration status at each leg, bunkers and provisioning, weather routing across monsoon-season passages, and port clearances at both ends. For vessels handed to foreign buyers, we align the commercial closing — funds, title transfer, deletion or first registration — with the physical departure so neither waits on the other.
Timing: when to start the export file
The export and flag file should open when the build or refit reaches roughly its final quarter — early enough for tonnage measurement, IMO assignment and registry pre-checks to run while the yard finishes, late enough that the documents describe the vessel as she will actually deliver. Files opened at handover week add weeks at anchor; files opened with us during construction deliver vessels that sail on the day the yard releases them.
Questions
Frequently asked questions
How do I register an Indonesian-built yacht under a foreign flag?
What export documents does a newly built vessel need?
How is gross tonnage calculated for export papers?
When is an IMO number required for an Indonesian-built vessel?
Can the desk manage delivery voyages to neighbouring countries?